For version EV2 installation, please go here.

*For Chinese subtitles, check out our Youku channel.

1) Intro

2) Components List

3) Preparing Installation

4) Mounting Data Transmitter

5) Installing Voltage Taps

6) Installing Verdigris Smart Current Transformers (CTs)

7) Installing High Current Interface Module (HCIM)

8) Installing Large Current Transformers

9) Connecting Large CTs to HCIM

10) Connecting Extension Cables

11) Connecting Voltage Taps

12) Securing Data Transmitter

13) System Check

14) Setting up Verdigris Current Transformers Module

15) Setting up High Current Interface Module (HCIM)

16) Checking Verdigris Setup

17) Troubleshooting

Did this answer your question?